Skip to main content

Notice: IDOC is transitioning its phone service to a new vendor. Please read more details and instructions to prepare here.

 

Menard and Shawnee CC are transitioning video visitation service from GTL to ICSolutions. More information is available here.

Key Dates

Initial Public Notice to CGFA: March 17, 2024

Recommendation Requested by CGFA: March 27, 2024

Recommendation Received by CGFA from IDOC: April 26, 2024

30-Day Public Comment Period: April 29, 2024 - June 1, 2024

CGFA Hearing (IDOC testimony)May 10, 2024

Local Meetings Scheduled:

Follow-Up Meeting Scheduled: June 14, 2024

Commission Recommendation: issued June 14, 2024

·       Stateville Correctional Center

·       Logan Correctional Center

CDB Posted Notice of Upcoming Request for Proposal for Construction Management and Owner’s Advisor: November 1, 2024

CDB Issued Construction Management and Owner’s Advisor Request for Proposal (RFP) ) PSB #317-2: November 19, 2024

CDB’s Deadline to Pre-Qualify for Initial Solicitation: December 16, 2024