Key Dates

Initial Public Notice to CGFA: March 17, 2024

Recommendation Requested by CGFA: March 27, 2024

Recommendation Received by CGFA from IDOC: April 26, 2024

30-Day Public Comment Period: April 29, 2024 - June 1, 2024

CGFA Hearing (IDOC testimony)May 10, 2024

Local Meetings Scheduled:

Follow-Up Meeting Scheduled: June 14, 2024

Commission Recommendation: issued June 14, 2024

·       Stateville Correctional Center

·       Logan Correctional Center

CDB Posted Notice of Upcoming Request for Proposal for Construction Management and Owner’s Advisor: November 1, 2024

CDB Issued Construction Management and Owner’s Advisor Request for Proposal (RFP) ) PSB #317-2: November 19, 2024

CDB’s Deadline to Pre-Qualify for Initial Solicitation: December 16, 2024